18 May, Ratnanagar (Chitwan): The Muglin-Narayangarh Road Project is resuming its construction works from today by stopping vehicular operation in the road stretch for six hours every day.

The Project that put road construction works on hold for 10 days in view of the May 14 local level elections has started its regular business from today.

According to Project Engineer Shiva Khanal, the Muglin-Narayangarch road section would remain closed for vehicles from 10.00 am to 4.00 pm from today until its completion.

He shared that only 47 % of the targeted works have been so far completed on the road section.

Some six companies have been involved in the construction of 34-km of road section in three phases.

The road widening and construction drive is taking place in the section with World Bank funding. RSS